Termination for Breach of Contract: Lessons and Key Takeaways

By Narman Aria

Trainee Solicitor

The Case of URE Energy Ltd v Notting Hill Genesis [2024] EWHC 2537 (Comm)

When you enter into a contract, you are often focused on the benefit the contract provides and less so on the termination provisions.  However, in circumstances where the other party is not performing their contractual responsibilities, and you are considering terminating a contract, the termination provisions in a contract become critical.  In any circumstance, terminating a contract is an important decision and if you get it wrong, you could be the party liable for loss.  The risks are, therefore, high and if not handled carefully, you could be liable for wrongful repudiation and find a claim being made against you for the other parties’ loss of profit, amongst other claims.

The High Court’s decision in URE Energy Ltd v Notting Hill Genesis examines how a company’s termination rights can be preserved—or lost—based on contract language and actions.  The below sets out some of the lessons we have learnt from that case. 

Case Overview: An Unexpected Termination Outcome

This case involved an electricity supply contract between URE Energy (URE) and Genesis Housing Association, later merged with Notting Hill Housing Trust to form Notting Hill Genesis (NHG). URE made an attempt to terminate the contract twice, attributing a right to do so if NHG merged without consent and alleging material breaches. Each attempt uncovered different legal issues and lessons.

Key Lessons and Practical Takeaways from the Case

1. The Role of Contract Language in Termination Rights

The contract allowed URE to terminate if NHG merged without prior consent. However, neither party initially recognised this right’s significance. When NHG merged without consent, it provided URE with an enforceable ground for termination in its second notice.

• Takeaway: Termination clauses, particularly those concerning structural changes like mergers, should be explicit. Clear, binary conditions such as “failure to obtain prior approval” are often more enforceable than subjective terms like “material breach.”

2. Waiver by Election: Knowledge and Prompt Action Matter

NHG argued that URE waived its termination rights by continuing the contract post-merger, indicating affirmation. Waiver by election requires actual knowledge of the termination right, which URE lacked until it obtained legal advice.

• Takeaway: To preserve termination rights, a party must act quickly and definitively once aware of grounds for termination. Businesses should consult legal advice promptly, as delay could suggest an intention to affirm the contract.  This, however, needs to be coupled with ensuring the appropriate necessary steps have been followed and ensuring the circumstances are sufficient to meet the grounds set out in any clause.  Documentation of legal advice can be crucial in demonstrating lack of knowledge.

3. Material Breach and Risks of Hurried Termination Notices

URE’s first termination attempt cited NHG’s failure to cooperate in installing smart meters as a “material breach.” However, without prior legal advice, this notice appeared rushed. Under contract law, a “material breach” generally requires substantial seriousness.

• Takeaway: Exercise caution in terminating for material breach; courts will assess if the breach meets the required threshold. Evidence demonstrating the seriousness of the breach, such as prior communications, is critical. Legal advice helps ensure the grounds for termination are sound.

4. The Value of a Measured Approach to Termination

URE’s initial hurry in issuing a termination notice without legal support risked it being seen as a wrongful repudiation. Fortunately, NHG did not immediately accept the repudiation, allowing URE to issue a more considered second notice that referenced both the merger and meter issues.

• Takeaway: “Measure twice, cut once.” Ensuring a fully substantiated basis for termination reduces risks of wrongful termination claims.

5. Termination Payments and Avoiding Penalty Clauses

Upon successfully terminating under the amalgamation clause, URE claimed a termination payment equivalent to 50% of the remaining contract value. The court upheld this, interpreting “remaining value” as charges rather than profits, aligning with the contract’s intent.

• Takeaway: Termination payment clauses should clearly outline the basis for “remaining value” calculations to prevent disputes. These clauses should be drafted in a way that aligns with contract intent and avoids classification as a penalty.

Note that the above lessons refer to a commercial contract.  All contracts are fact specific and need to be considered on their own merits.  The rules for construction contracts are different and if you have a construction contract, we can offer you tailored advice. 

Conclusion

The URE Energy case underscores the complexities of terminating contracts, particularly with layered termination provisions. By drafting clear termination rights and carefully assessing grounds for termination, businesses can avoid drawbacks. Acting in hurry, especially without legal advice, could lead to costly mistakes.

The time to consider termination clauses is when you are negotiating the terms of a contract, and our excellent Company Commercial Team are on hand to assist with drafting any contract you may wish to enter into.  However, if you’ve already entered a contract and considering contract termination or want to review your termination clauses, our commercial litigation team can provide guidance and a clear strategy to move forward and limit your exposure to risks.